• Construction of 12th and 13th  floors of the building has been finished in Ocotber and 14th floor has been started.

    October, 2018

    Construction of 12th and 13th floors of the building has been finished in Ocotber and 14th floor has been started.

  • Construction of 11th floor of the building has been finished in September and 12th floor has been started.

    September, 2018

    Construction of 11th floor of the building has been finished in September and 12th floor has been started.

  • Construction of 9th and 10th floors of the building have been finished in August and 11th floor has been started.

    August, 2018

    Construction of 9th and 10th floors of the building have been finished in August and 11th floor has been started.

  • Construction of 7th and 8th floors of the building have been finished in June and 9th floor has been started.

    July, 2018

    Construction of 7th and 8th floors of the building have been finished in June and 9th floor has been started.

  • Construction of 5th and 6th floors of the building have been finished in June and 7th floor has been started.

    June, 2018

    Construction of 5th and 6th floors of the building have been finished in June and 7th floor has been started.

  • Construction of 4th floor of the building has been finished and 5th floor has been started.

    May, 2018

    Construction of 4th floor of the building has been finished and 5th floor has been started.

  • Construction of undergournd parking and two commercial levels has been finished.

    April, 2018

    Construction of undergournd parking and two commercial levels has been finished.

  • Placement of slabs on the -2 level has been finished.

    March, 2018

    Placement of slabs on the -2 level has been finished.

  • Placement of slabs on the -2 level has been started.

    February, 2018

    Placement of slabs on the -2 level has been started.

  • Construction of pillars, beams and diaphragms on the -2 level has been finished.

    February, 2018

    Construction of pillars, beams and diaphragms on the -2 level has been finished.

  • Construction of pillars, beams and diaphragms, and placement of moulds has been started.

    February, 2018

    Construction of pillars, beams and diaphragms, and placement of moulds has been started.

  • Construction of tile (pillow layer) has been finished.

    January, 2018

    Construction of tile (pillow layer) has been finished.

  • Construction of piles has been finished.

    January, 2018

    Construction of piles has been finished.